Summerville Stormwater Retention Pond

SILD Field Notes

    The Town of Summerville contracted SILD to create a new 2.6 acre stormwater pond. Clearing the heavily wooded site was done carefully and quickly to cause minimal disturbance to nearby residents. Approximately 38,000 cubic yards of dirt was removed to form the new stormwater pond.  SILD completed the majority of earthwork excavations in a 1 month span. 